Project Execution Workflow

End-to-End Lifecycle Matrix

STAGE 0: Initiation
Sales Team
  • Mr. Manish Gupta
  • Shashikanth Tripathi
Leadership hands over order to Sales to initiate on ydproject.ydagchmi.com/kickoff.

Submit Client name, site, product & S.O Number. Choose if Electrical Design only.
SLA : 7 days
⚠️ Auto Escalate if not honoured to : Mr. Navneet Singh & Mr. Sameer Bansal
STAGE 1: Project Number Allocation
Design Team
  • Mr. SK Tripathi (Director)
  • Surajpal Singh (Electrical)
  • Sanjay N. & Krishna P. (Mumbai)
  • Vinit J, Smith K, Brajraj (Mech)
Allocate Project Number from PDM and enter description of the product.
⏱️ SLA: 24 Hours
⚠️ Auto Escalate if not honoured to : Mr. Navneet Singh & Mr. Sameer Bansal
STAGE 2: Director's Decision
Directors
  • Mr. Navneet Singh
  • Mr. Sameer Bansal
Select Project Path:

● Proceed AFTER Advance
● Proceed WITHOUT Advance
NO ADVANCE
ADVANCE
STAGE 3: Advance Handling
Finance & Sales
  • Mr. Sameer Bansal & CFO Anup Sharma
  • Vikas S. & Ajay U. (Finance)
  • Mr. Manish G. & Shashikanth T. (Sales)
Clock advance payment and upload official receipt to the flow.
⏱️ SLA: 15 Days
⚠️ Auto Escalate if not honoured to : Mr. Navneet Singh & Mr. Sameer Bansal
STAGE 4: PM Allocation
Leadership
  • Mr. Varun Jay Rana (COO)
  • Mr. Aseem Gill (VP Projects)
Allocate Project Manager.

Trigger alerts to PM, Design Teams, and Sales to prepare scope in advance.
⏱️ SLA: 2 Days
⚠️ Auto Escalate if not honoured to : Mr. Navneet Singh & Mr. Sameer Bansal
STAGE 5: Kickoff Meeting
Execution
  • Allocated Project Manager
Conduct kickoff meeting with Management, Sales, Electrical, Mechanical & Mumbai Design

Submit Minutes of Meeting (MoM) for the project.
⏱️ SLA: 2 Days
⚠️ Auto Escalate if not honoured to : Mr. Navneet Singh & Mr. Sameer Bansal
STAGE 6: Realisation
System Action
  • 💻 Realisation Tool
Project Handover Complete

Project starts running with its active planning mapped in the tool.

⚡ Global Alerts

System triggers instantly via WhatsApp & Email.

📈 Executive Reporting

Initiated/Running lists sent to Directors Every Monday.

👥 Escalation Matrix

Directors Mr. Navneet Singh & Mr. Sameer Bansal
COO/VP Mr. Varun Jay Rana & Mr. Aseem Gill

STAGE 6: Tentative Billing Schedule
Planning & Forecasting
  • Mr. Shivendu Sharma
Scope of Supply discussion with Sales and Mechanical Design Team just after Kickoff Meeting.

Tentative Billing Schedule sheet to be uploaded with:
  • PROJECT (e.g., 2428-BMWIL-CGL)
  • ASSEMBLY
  • DISPATCH MONTH & BILLING VALUE
⏱️ SLA: 7 Days
⚠️ Escalate: Navneet Singh / Sameer Bansal
STAGE 7: Dispatch Schedule
Design Team
  • Mr. SK Tripathi (Director)
  • Surajpal Singh (Electrical)
  • Sanjay N. & Krishna P. (Mumbai)
  • Vinit J, Smith K, Brajraj (Mech)
Dispatch Schedule received.

Design Department to enter Drawing Release Date for every assembly.
⏱️ SLA: 2 Days
⚠️ Escalate: Navneet Singh / Sameer Bansal
STAGE 8: COO/VP APPROVAL
Executive Approval
  • Mr. Aseem Gill (VP)
  • Mr. Varun Jay Rana (COO)
Reviews tentative design release dates.

Once approved, all delivery dates are 🔒 LOCKED.
⏱️ SLA: 7 Days
⚠️ Escalate: Navneet Singh / Sameer Bansal
STAGE 9: Director's Approval
Directors
  • Mr. Navneet Singh
  • Mr. Sameer Bansal
Reviews and approves the Tentative Billing Schedule.

Access: Shivendu Sharma, Aseem Gill, Navneet Singh & Sameer Bansal
STAGE 10: Billing Schedule
Accounts & Customer
Full Tentative Billing Schedule consisting of:
  • PROJECT & ASSEMBLY
  • DISPATCH MONTH & VALUE
STAGE 11: Upload Drawings
Design Team
Uploads Drawings on the website.

Change Request Form required for changes. Only latest version available.
STAGE 10: Eng + SAP + Segregation
Owner
  • Design Team
SCOPE:
Full breakdown of component structure and hierarchical segregation. Assignment of WBS to individual parts.
SYSTEM LOGIC:
Enforces exact parent-child relationships (Assemblies → Subassemblies → Components) and validates Drawing Number, Revision, Quantity, and Material before proceeding.
STAGE 11: SAP + PO Generation
Owner
  • Purchase Team
SCOPE:
Vendor allocation, strict SAP mapping for required components, and finalization of PO values.
SYSTEM LOGIC:
Automatically fetches component demands from Stage 10. Links SAP item codes to generated PO numbers and locks the mapped value allocation.
STAGE 12: Component Tracking
Owner
  • Store + PM
SCOPE:
End-to-end component tracking lifecycle from dispatch at vendor to factory receipt.
SYSTEM LOGIC:
Status dynamically transitions (Ordered → In Production → Received). Store teams authenticate physical receipts via SAP GRN matching.
STAGE 13: Assembly + Production
Owner
  • Shop Floor
SCOPE:
Assembly execution on the floor based on matched full-kits and production scheduling.
SYSTEM LOGIC:
Production run is strictly gated by SAP Full Kit logic. Cannot commence assembly unless all prerequisite components from Stage 12 are marked as 'Received'.
STAGE 15: Dispatch
Owner
  • Logistics
SCOPE:
Physical dispatch of fully assembled and invoiced machineries to the client site.
SYSTEM LOGIC:
Dispatch documentation is structurally linked to the Stage 14 invoice. Gate pass generation blocked until invoice validation is confirmed.
STAGE 14: Invoicing
Owner
  • Accounts
SCOPE:
Financial verification and assembly-wise invoice generation for completed units.
SYSTEM LOGIC:
Triggers revenue realization logic. Synchronizes completed assemblies from the shop floor directly into the billing queue.